23題: The information security management system preserves the confidentiality ,integrity and availability of information by applying a/an( ) management process and gives confidence to interested parties.
A.quality
B.information
C.risk
D.data
答案解析與討論:
www.yifanwine.com/st/11020919343.html第
24題: ( )describes the configurable items of the project and identifies the items that will be recorded and updated so that the product of the project remains consistent and operable.
A.The configuration management plan
B.The change management plan
C.The requirements traceability matrix
D.The change baseline
答案解析與討論:
www.yifanwine.com/st/11021023727.html第
25題: When required, the Perform Integrated Change Control Process includes a( ),which is a formally chartered group responsible for reviewing evaluating, approving, deferring or rejecting changes to the project and for recording and communicating such decisions
A.BBC
B.CCB
C.BCB
D.CBC
答案解析與討論:
www.yifanwine.com/st/110211829.html