試題內(nèi)容

When reviewing an active project, an IS auditor observed that, because of a reduction in anticipated benefits and increased costs, the business case was no longer valid. The IS auditor should recommend that the: 
A、project be discontinued. 
B、business case be updated and possible corrective actions be identified. 
C、project be returned to the project sponsor for reapproval. 
D、project be completed and the business case be updated later. 