The project manager’s analysis concludes the project’s cost performance index is at 80%.The project’s actual cost to date is US$100,000, but the project was predicted to cost US$120,000 to date. What is the project’s schedule performance index?
	A、0.96
	B、0.83
	C、0.76
	D、0.67