The project manager is managing a complex project. The team members come from all over the world、 The project schedule plan has been completed, but also needs to detail integrate the project package and the buyer’s work package. Which of the following tools would be used to manage the project ?
A、Configuration management system
B、 Historical information
C、 Work authorization system
D、 Change control board