試卷名稱(chēng) 信息系統(tǒng)項(xiàng)目管理師-pmp練習(xí)題-1
考試中心《信息系統(tǒng)項(xiàng)目管理師-pmp練習(xí)題-1》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內(nèi)容

The project has finally completed, however, the project was delayed, causing cost overruns at the end of project. What should the project manager do in this case?
A、Record the circumstances as lessons learned
B、 Concentrate on archiving the financial records for this project.
C、 Collect all the work of the project and compare the results to the project scope.
D、 Record the circumstances surrounding project completion during the scope validate process.