The project manager creates the integrated change control system at the start of a project. Using this system, which of the impact changes should be made a change request ?
	A、Resources, schedule, cost and risk mitigation.
	B、 Plan, schedule, cost and quality.
	C、 Resources, schedule, cost and quality.
	D、 Resources, risk mitigation, cost and quality.