亚洲免费a,激情久久av,www.色就是色.com,全黄a免费一级毛片人人爱,久久精品中文字幕大胸,欧美三级视频在线观看,日韩一级大黄

軟題庫 移動APP 掃碼下載APP 隨時隨地移動學習 培訓課程
試卷名稱 信息系統(tǒng)項目管理師-pmp練習題-2
考試中心《信息系統(tǒng)項目管理師-pmp練習題-2》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內(nèi)容

The project manager checks the scope statement against the work results for the project deliverables to ensure consistency. The results should be documented and used by the project manager for which of the following ?
A、Validating the quality process.
B、Estimating future projects.
C、Defining tasks for future projects.
D、Changing the project scope.


相關試題

推薦文章
合作網(wǎng)站內(nèi)容