亚洲免费a,激情久久av,www.色就是色.com,全黄a免费一级毛片人人爱,久久精品中文字幕大胸,欧美三级视频在线观看,日韩一级大黄

軟題庫 移動APP 掃碼下載APP 隨時隨地移動學習 培訓課程
試卷名稱 信息系統(tǒng)項目管理師-pmp練習題-2
考試中心《信息系統(tǒng)項目管理師-pmp練習題-2》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內容

A project manager leads a project to build a data center. The client submits a dramatic change to the project manager. Insisting that modification must be introduced as soon as possible involves incremental changes to the budget and an expectation of the overall schedule. What should the project manager do next ?
A、Advise the client to initiate the change as another project.
B、Present the client’s request at the next change control board meeting.
C、Include the client’s change and re-baseline the budget and schedule.
D、Ignore the request as the baseline for the budget and schedule have been agreed to.


相關試題

推薦文章