A core project team performed the initial phase of the project stakeholder analysis. The results of the analysis show that a few stakeholders on the project has some negative effect. What should the project manager do next ?
	A、Update the project risk log with the project and analysis results.
	B、Engage the stakeholders to understand their project expectations.
	C、Develop a communication management plan based on the analysis.
	D、Develop a plan to manage stakeholder engagement levels.