亚洲免费a,激情久久av,www.色就是色.com,全黄a免费一级毛片人人爱,久久精品中文字幕大胸,欧美三级视频在线观看,日韩一级大黄

軟題庫(kù) 移動(dòng)APP 掃碼下載APP 隨時(shí)隨地移動(dòng)學(xué)習(xí) 培訓(xùn)課程
試卷名稱 2017年信息系統(tǒng)項(xiàng)目管理師最新英語(yǔ)模擬題(1)
考試中心《2017年信息系統(tǒng)項(xiàng)目管理師最新英語(yǔ)模擬題(1)》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內(nèi)容

Impact scores.A project team identifies several risks and assesses probability of occurrence and potential impact on cost, schedule, and performance for each risk. This information is presented in the table shown.If meeting cost objectives is the highest priority for this project. Which is the most critical risk for the project team to address?

A、Risk A

B、Risk B

C、Risk C

D、Risk D



相關(guān)試題

推薦文章