亚洲免费a,激情久久av,www.色就是色.com,全黄a免费一级毛片人人爱,久久精品中文字幕大胸,欧美三级视频在线观看,日韩一级大黄

軟題庫 移動APP 掃碼下載APP 隨時隨地移動學(xué)習(xí) 培訓(xùn)課程
試卷名稱 2017年信息系統(tǒng)項目管理師最新英語模擬題(1)
考試中心《2017年信息系統(tǒng)項目管理師最新英語模擬題(1)》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內(nèi)容

Weather conditions are identified as critical risks for an offshore wind park development project. To mitigate risks associated with bad weather conditions, the project manager creates a contingency plan to and more time to the planned schedule. At the time of execution a hurricane comes close to the wind park area so that all activities need to be stopped immediately.What should the project manager next?
A、Update the risk register and create a change request.
B、Get additional approval from the steering committee.
C、Change the schedule of the team members accordingly
D、Avoid any chances to keen the project management plan as if was approved.


相關(guān)試題

推薦文章
合作網(wǎng)站內(nèi)容