試卷名稱 2017年信息系統(tǒng)項(xiàng)目管理師最新英語模擬題(1)
考試中心《2017年信息系統(tǒng)項(xiàng)目管理師最新英語模擬題(1)》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內(nèi)容

The customer asks the project manager to have the system online within one week, There are still bugs in the system, but the project manager wants to meet the customer’s desire to have the system running on time.The project manager should choose which of the following risk strategies?
A、Mitigate
B、Accept
C、Transfer
D、Avoid