試卷名稱 2017年信息系統(tǒng)項(xiàng)目管理師最新英語(yǔ)模擬題(3)
考試中心《2017年信息系統(tǒng)項(xiàng)目管理師最新英語(yǔ)模擬題(3)》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內(nèi)容

If the end date of an initial plan is later than the desired date, what is the FIRST action the project manager should consider?
A、Reviewing current resource on the project
B、Determining whether more work can be done in parallel
C、Starting critical path activities at their early start dates.
D、Negotiating a change in scope for an activities with negative float