How should a project manager interpret an 8-point run in a process with 1 point located out of control limit?
	A、It is a normal situation, nothing should be done.
	B、Control limits should be widened.
	C、It is an abnormal situation; production processes should be corrected.
	D、It is a warning signal; quality measurement systems should be updated.