亚洲免费a,激情久久av,www.色就是色.com,全黄a免费一级毛片人人爱,久久精品中文字幕大胸,欧美三级视频在线观看,日韩一级大黄

軟題庫(kù) 移動(dòng)APP 掃碼下載APP 隨時(shí)隨地移動(dòng)學(xué)習(xí) 培訓(xùn)課程
試卷名稱 2017年信息系統(tǒng)項(xiàng)目管理師最新英語(yǔ)模擬題(4)
考試中心《2017年信息系統(tǒng)項(xiàng)目管理師最新英語(yǔ)模擬題(4)》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內(nèi)容

The project manager discovers an unpredictable high-impact risk has become a factor in the project. self-interest among team members is keeping the issue from being reached, The project manager must act quickly to refocus the team and get the project on tack. which of following techniques should the project manager use to resolve the issue?
A、Compromise
B、Collaborate
C、Force
D、Accommodate


相關(guān)試題

推薦文章