試卷名稱 2017年信息系統(tǒng)項(xiàng)目管理師最新英語模擬題(5)
考試中心《2017年信息系統(tǒng)項(xiàng)目管理師最新英語模擬題(5)》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內(nèi)容

The method of calculating the EAC by adding the remaining project budget (modified by a performance factor) to the actual to date is used most often when the
A、Current variances are viewed as atypical ones
B、Original estimating assumptions are no longer reliable because conditions have changed
C、Current variances are viewed as typical of future variances
D、Original estimating assumptions are considered to be fundamentally flawed